Global Journal of Engineering Sciences (GJES)
Effect
Analysis of Different Treatment Methods for Soft Soil Foundation of Highway
Authored by Hong-Jun Liu
Abstract
With
the rapid development of Guangdong, Hong Kong and Macao Bay area, the intercity
rapid traffic network with high-grade highway as the main part has been
developed rapidly. At the same time, the technology related to the soft soil
foundation treatment of highway has also been developed. Based on a highway
project in Foshan, Guangdong, this research used on-situ monitoring to study 4
kinds of soft soil foundation treatment methods, including preloading method,
cement mixing pile, high-pressure jet grouting pile and Cement Flying-ash
Gravel (CFG) pile, and then comparatively analyzed the influence of different treatment
methods on the settlement of soft foundation. Finally, hyperbolic method was
used to calculate the final settlement and post-construction settlement. The
results showed that under the similar thickness of soft soil layer, treatment
depth and filling height, CFG pile and high-pressure jet grouting pile have the
best effect of controlling settlement after construction, which are 8.638mm and
14.584mm respectively; Cement mixing pile was followed by 23.196mm; preloading
method are the worst at 71.731mm. In addition, the cumulative settlement of the
preloading method is the largest, which are 212mm; the cement mixing pile is
the second, which are 160mm; the CFG pile and the high-pressure jet grouting
pile are the smallest, which are 120mm and 132mm, respectively. The research
results provide a basis for the design and construction of soft soil foundation
treatment for highway in the future.
Keywords: Treatment effect of highway soft
soil foundation; Bagged sand well; Cement mixing pile; High- pressure jet grouting
pile; CFG pile
Introduction
Soft
soil [1] refers to fine-grained soil which natural void ratio is greater than
1.0 and natural water content is greater than the liquid limit. It includes
silt, silty soil, peat and peaty soil, etc. In the construction of highway, due
to the soft soil has low bearing capacity and high compressibility, the
subgrade will inevitably collapse and uneven settlement if proper methods are
not taken to deal with it. At present, there are many treatment methods for
highway soft soil foundation, such as sand wick stacking load and consolidated
drained technique, cement mixing pile, high-pressure jet grouting pile and CFG
pile.
The
bagged sand well [2] is by applying a load step by step on the soft soil
foundation and draining the pore-water from the soil by vertical drainage such
as bag sand-well, so that the soft soil foundation is consolidated and settled,
which will improve the strength of soft soil. The cement mixing pile [3] is a
method to make the soft soil harden gradually and improve foundation strength
through injecting cement into the depth of foundation and mixing with soft soil
with special mixing equipment. High-pressure jet grouting pile [4] is a method
to replace soft soil layer and squeeze around the pile through spraying cement
slurry into soil rapidly. CFG pile [5] is made of cement, fly ash, crushed
stone, gravel or sand mixed with water to form a high bonding strength pile,
and it forms a composite foundation together with pile layer and mattress.
Based
on the highway project from Gaoming Bridge to Fulong Bridge in Foshan, the
subsidence monitoring analysis of the above 4 kinds of soft soil foundation
treatment is carried out. By using hyperbolic method, the final settlement of
highway roadbed and post-construction settlement of highway roadbed are
calculated. Relying on the quantitative data, this paper analyzes the treatment
effect of soft soil foundation from the perspective of engineering technology
and provides the basis for the design and construction of similar soft soil
foundation treatment.
Project Overview and Geological Situation
Project overview
The
project is the highway project from Gaoming Bridge in Foshan city to Fulong
Bridge, namely the north extension line of Yangxi Avenue. The length of the route
is about 9.020km, and the stake number ranges from K27+ 780 to k36+800. It is
arranged according to the two-way 6-lane section and adopts the first-class
highway standard to take into account the function of urban roads. The design
speed of the main road is 80km/h, and the design speed of the auxiliary road is
40km/h.
Geological situation
The
landform along the project is mainly alluvial plain and denudation monadnock.
Most of the surface is farmland and fishpond, with abundant water source. The
research area is alluvial plain, which is the plain area on the West Bank of
the Pearl River Delta. The main mileage is from K27+800 to K30+150, K31+450 to
K31+750, k32+000 to k33+650, k33+900 to K37+150. It belongs to the first
terrace of Quaternary sedimentation, with flat terrain and abundant water
sources around. The ground elevation is generally 3.0-11.0m. The overlying soil
layer is mainly quaternary alluvial cohesive soil and sand, and some of the
overlying soil layers are special soil layers, such as developed soft soil and
saturated liquefied soil, in local fishponds, rivers and ditches. The
underlying bedrock is the upper Cretaceous (K2ss), upper Triassic (T3x) and
lower Carboniferous (C1s).
According
to the survey results, the foundation overburden along the line was composed of
artificial fill (Q4ml), Quaternary Holocene fluvial facies alluvium (Q4al),
(Q3el), the upper Cretaceous (K2ss), upper Triassic (T3x) and lower
Carboniferous (C1s). The basic physical and mechanical properties of soft soil
The settlement plate consisted of a steel
plate, a measuring rod and a protective sleeve, as shown in Figure 1. The site
setting out was carried out according to the coordinates of the design drawing,
and the excavation was carried out manually to the original ground. After
clearing the pit bottom, lay a 3~5cm thick fine sand cushion and then put the
settlement plate on the sand cushion to ensure the bottom plate was flat and
stable. Subgrade settlement monitoring was mainly carried out by geometric
leveling method. During the filling stage, the accuracy level of leveling was
grade III. But during the preloading period, the accuracy level of leveling was
grade II. As the embankment was filled high, the settlement plate pole and
protective casing were increased section by section. The height of each section
was 50cm. In order to obtain the settlement of this period and the initial
elevation before the next measurement, elevation was measured before and after
connecting the rod
Selection of monitoring
section for surface subsidence
The layout of settlement
monitoring points is shown in Figure 3.
In order to compare and
analyze the effects of the four treatment methods, four monitoring sections
with similar soft soil thickness, filling height and treatment depth were
selected for study. The soft soil thickness, filling height and treatment depth
of each monitoring section.
Effect Analysis of Four Soft Soil Foundation Treatment Methods
Analysis of ground settlement
Ground settlement was the
basis for the analysis of soft ground settlement. Its change rule was not only
the most important target for controlling the construction schedule and
arranging later construction, but also the most direct test standard for
judging whether the theoretical research results were correct. In this project,
thin-Layer Intermittently Adding Method [6] was adopted for filling, and each
layer of filling was about 40cm. During the monitoring of soft soil foundation,
each fill layer was monitored once. After the completion of embankment filling,
it would be monitored every 5 days until the preloading period was completed.
By analyzing the above
curves, the following conclusions can be drawn:
• At the same filling height,
the settlement of foundation was closely related to the filling thickness. The
total settlement of the above four soft foundation treatments increased with the
increase of filling height, and all of them show certain regularity. During the
filling, the settlement curve generally appeared obvious subsidence phenomenon,
and the change was steep; During the period of constant load, the settlement
changed slowly and gradually flattens out in the later period. In addition to
the preloading method of packed sand well, the curve convergence of the other
three methods was faster in the preloading period.
• By comparing the settlement
process of the left, middle and right settling plates, it could be found that
the settlement amount of the middle settling plate was generally greater than
that of the left and right settling plates, which was consistent with the
distribution principle of additional stress.
• That was to say, the
additional stress on the horizontal plane at the same depth under the ground
was different, the additional stress along the line of action of the force was
the largest, and gradually decreases toward both sides.
• At a similar filling height,
when the pile was loaded to the 200th day, the accumulated settlement of the
bagged sand well was 212mm; the cement mixing pile was 160mm; the highpressure
jet grouting pile and the CFG pile were 132mm and 120mm respectively. From the
perspective of technology, the bagged sand well method was different from the
other three methods. The bagged sand well method was to put the sand and gravel
into the long bag of pervious geotextile and set it in the soft soil foundation
to form a drainage channel. And under the load, as the excess pore-water
pressure dissipated gradually, the effective stress of the soil itself
increased gradually to make the strength of the foundation soil increase
gradually. However, the foundation treated by cement mixing pile, high pressure
jet grouting pile and CFG pile was composite foundation with piles and cushion
[7]. It was composed of two parts, the matrix and the reinforcement, which were
two kinds of materials with different stiffness modulus. Under the load, the
pile and the soil between the piles shared the upper load and coordinated the
deformation; Therefore, the settlement control effect of composite foundation
with piles and cushion was better than that of bagged sand well under the
similar filling height.
Analysis of surface subsidence rate
Settlement rate could directly
reflect the speed of embankment settlement in the process of loading and it was
one of the important indexes to control the speed of filling. In the process of
loading, the settlement and stability should be monitored synchronously. The
filling rate was strictly controlled, and the control standard was the central
settlement rate of embankment less than 10mm/d.
According to the monitoring
data, the intermediate settling plates in the four methods were selected for settlement
rate analysis. The settlement rate cure is shown in Figure 9.
By analyzing the settlement
rate curve in Figure 9, the following conclusions can be drawn:
• “Thin-Layer Intermittently
Adding Method” was used for filling, and the monitoring data results showed
that the settlement rate was not more than 10 mm / D, and there was no overall
sliding failure on site. It had been proved that this method, which was an
economic, applicable and reasonable scientific method, increased the stability
of embankment construction and is
• The maximum settlement rate
of bagged sand well, cement mixing pile, high-pressure jet grouting pile and
CFG pile appeared in the loading period, the values were 6.33mm/d, 5.50mm/d,
3.67mm/d and 4.50mm/d respectively.
This showed that the
settlement rate had a rapid increase process with each stage of loading, and
then gradually became slow convergence;
In the later period of
constant load, the settlement rate gradually tended to be stable.
In the whole process, the
curve changed very slowly until the curve tended to level, which showed that
the settlement process of the whole embankment was basically completed.
• In terms of the above four
kinds of soft foundation treatment effect, the settlement effect of composite
foundation with piles and cushion should be better than that of bagged sand
wells. This was because under the load, the friction between pile and soil was
increased through deformation, which improved the bearing capacity of
foundation. In this way, the settling rate decreased in the later period of
constant load, which indicated that the settlement of the foundation was
limited.
• As far as bagged sand wells
were concerned, the larger value of the settlement rate usually occurred in the
filling period. While during the preloading period, the settlement rate was
obviously reduced, which showed that the bagged sand well played a good role in
drainage consolidation to make the consolidation degree of the soft soil
foundation improve and to control the subgrade settlement.
• As far as the pile composite
foundation is concerned, the effect of high-pressure jet grouting pile and CFG
pile was better than that of cement mixing pile on controlling settlement rate.
This showed that the method of spraying cement slurry into the soil layer
through a high-pressure rotating nozzle was better than the method of mixing
cement into the soil layer through a mixer at a low speed.
Compared with the cement
mixing pile, CFG pile was mixed with gravel, sand, fly ash, which could
increase the stiffness of the pile and improved the bearing capacity of the
foundation, so the effect of settlement control was increased by about 25%.
Calculation and Analysis of Subgrade
Final Settlement and Post-Construction Settlement
At present, the methods to
predict the settlement by the monitoring data included hyperbolic method [8],
exponential curve method, settlement rate method, three-point method, Poisson
method, etc.
Among these common methods,
the consolidation degree calculated by hyperbolic method was conservative,
which was more favorable for engineering practice, so hyperbolic method was
commonly used in engineering.
In the analysis of the
monitoring data, it was found that the settlement had a good hyperbolic
relationship with time, so the hyperbolic method was used in this project to
calculate the final settlement and post construction settlement.
According to the monitoring
results of surface subsidence, the final settlement and post construction
settlement were calculated by hyperbolic method. On the basis of specification,
the middle pile was selected as the calculated object. The steps to determine
the settlement calculation are as follows:
• Determine the starting time
(T0). In this paper, the starting time was taken after the last stage of
subgrade filling construction was loaded;
• According to the monitoring
data, “Δt-Δt /ΔS” curve was drawed to determine the coefficient ɑ and β;
• Calculated S∞;
• Calculated St;
• Fitting and comparison were
carried out according to the formula.
y = βx +α (1)
The final settlement and post-construction
settlement calculated by hyperbola are shown in Table 3. The fitting curve is
shown in Figure 10.
• According to the
calculation results of the hyperbolic method, it could be found that the
post-construction settlement of the above four treatment methods was less than
the 20cm required by the specification. This indicated that these four methods
were feasible and effective for the treatment of soft soil subgrade in highway
engineering. Among them, high-pressure jet grouting pile and CFG pile had the
best effect in controlling post construction settlement, with post construction
settlement values of 8.638 mm and 14.584 mm respectively; followed by cement
mixing pile and bagged sand well, which was 23.196 mm and 71.731 mm
respectively.
• Compared with the actual
post-construction settlement, the final settlement calculated above might not
be absolutely accurate. This was due to the complexity, variability, and
randomness of the geological conditions. For example, the damage of the
settlement plate would bring certain errors to the calculated settlement
results. However, it could show the subsidence volume and its development trend
from the macroscopic view.
• The hyperbolic method was
used to calculate the settlement after construction of four soft foundation
treatment methods, and the correlation coefficient “R2” of curve fitting was
greater than 0.93, which showed that the results of the hyperbolic calculation
and the monitoring data were highly correlated and credible.
However, it could be found
that the large deviation between the fitting curve and the monitoring data
mainly occurred 80 days before the constant load, and then the deviation
between the two decreased after 80 days from Figure 10. This error was mainly
due to the preliminary construction machinery for embankment frequently caused
by the repeated rolling. Although the time of the construction machinery
passing on the embankment was short, the additional stress of the self-weight
on the soft soil foundation could not be ignored, especially the rolling of the
embankment by the construction machinery with large tonnage (such as the full
load dump truck, roller, etc.). This is the main reason for the settlement in
the early period of preloading, but the law of settlement growth in the preloading
period of soft soil foundation was obscured. Therefore, the fitting deviation
of the settlement curve in the early period of preloading was obviously lower
than that in the middle period.
Conclusion
Taking a highway project in
Foshan, Guangdong as an example, the four soft foundation treatment methods of
bagged sand well, cement mixing pile, high-pressure rotary jet pile and CFG
pile were studied, and the following conclusions were drawn:
• Under the similar thickness
of soft soil, treatment depth and filling height, the settlement of the
foundation treated by the above four soil soft foundation treatment methods is
closely related to the filling height, and the total settlement of the
foundation increases with the increase of filling height. In addition, the
slope of the settlement curve of the four treatment methods is relatively steep
during the stage loading. But after the loading is completed, the settlement
curve gradually tends to be gentle, which shows that the settlement of the
foundation is limited. It conforms to the compression settlement law of the
foundation.
• Based on the analysis of
monitoring data, at a similar filling height, the accumulated settlement of the
bagged sand well reach the maximum at the 200th day of stacking, reaching
212mm, followed by the cement mixing pile, reaching 160mm. and the
high-pressure jet grouting pile is similar to the CFG pile, reaching 132mm and
120mm respectively. And four kinds of soft soil foundation treatment methods
can effectively control the total settlement of the foundation.
• In the process of
preloading, on-site monitoring was used to effectively control the loading rate
and reasonably arrange the construction schedule, in which the maximum daily settlement
rate was 6.33mm/d for the bag sand well and 3.67mm/d for the CFG pile. And
during this period, the soft soil foundation did not appear obvious slip
phenomenon, which ensured the stability and safety of embankment in the loading
process.
• The hyperbolic method is
used to calculate the final settlement and post construction settlement of soft
soil subgrade. The results show that the high-pressure jet grouting pile and
CFG pile have the best effect in controlling post construction settlement, with
the minimum value of post construction settlement of 8.638 mm and 14.584 mm for
each, followed by cement mixing pile, with 23.196 mm, and the bagged sand well
is poor, with 71.731mm.
• After considering the
construction cost, construction period and construction difficulty, cement
mixing pile has a higher property value in the treatment of soft foundation in
these four methods, which provides a reference for the comparison and selection
of early schemes for similar projects.
For
more about Iris Publishers
please click on: http://irispublishersgroup.com/submit-manuscript.php.
To read more about this article - https://irispublishers.com/gjes/fulltext/effect-analysis-of-different-treatment-methods-for-soft-soil-foundation-of-highway.ID.000629.php
Indexing List of Iris Publishers: https://medium.com/@irispublishers/what-is-the-indexing-list-of-iris-publishers-4ace353e4eee
Iris
publishers google scholar citations: https://scholar.google.co.in/scholar?hl=en&as_sdt=0%2C5&q=irispublishers&btnG=

Comments
Post a Comment